In a year, we will go by tram from Ujeścisko to the center

Nowa Warszawska in Gdansk. Construction phase beginning March 2022.

500 meters of track, 66 traction shafts and 25 lights were installed during the year of work on the construction of the Nowa Warszawska tramway. The bike path is already about 65 percent complete. The works will end in November, and we will be operating the new line within a year.

Establishment of a tram road connecting Al. Havela started with the Ujeścisko loop exactly a year ago. It is operated by MTM and Rajbud. The cost of the investment is approximately 60 million PLN.

The length of the new tram line will be approximately 2 km. There will be a bike path and pedestrian path running along the path. As part of the work, intersection with Al. Havel for the new road to stick to the line Helmet – ostowice.

So far, nearly 500 meters of the track have been extended. Currently, work is concentrated in the department of the Mujahideen. Piotrkowska to Ujeścisko loop – reaches Zbigniew KordułaContract engineer on behalf of Gdansk City Development Directorate. – In the section of the Mujahideen. Lodzka to ul. Piotrkowska 100 percent. Tracks with tamping and polishing. You can also note what the platforms look like in ul. Lodzka and Mule. Piotrkowska.

66 traction shafts have already been installed along the route, and nine more will be built by the end of the week. There are also 25 lampposts.

The bike path and sidewalks are 65 percent ready.

Along the tram route, a bicycle path and sidewalks are created at the same time. Business progress in individual divisions ranges from 55 to 85 percent.

Close to st. Havel is already about 60% complete, in the section of the ul. Lodzka to ul. Piotrkowska – about 85 percent, behind the intersection with ul. Piotrkowska about 55 percent, and in the section at Ujeścisko station – about 60 percent.

Building Nowa Warszawska: Difficulties for the Mujahideen. Piotrkowska

In the near future, works will focus on the section near the Ujeścisko tram stop (before the intersection of Al Adamowicza, Jabłoniowa and ul. Lawendowe Wzgórze), that is, the farthest – from a city center perspective. Gdansk – end of the road.

In about two weeks, in early March and April, workers will begin work at the intersection of the tramway with ul. Piotrkowska. will be associated with Input the shuttle movement on the segment in the track area. To reduce inconvenience to residents, traffic will be controlled manually.

Nowa Warszawska: startup early 2023

The investment schedule stipulates that the works will be completed in November 2022. After that, the acceptance procedures will begin, which may take about three months. The new tram line will be launched in the first quarter of 2023.

The construction of Nowa Warszawska is being implemented as part of the Gdansk City Transport Project, which is co-financed by the European Union from the Cohesion Fund under the 2014-2020 Infrastructure and Operational Environment Program.

Leave a Reply

Your email address will not be published. Required fields are marked *

You May Also Like

Changes at the head of Polish State Railways. There is a new president

“On March 29, 2024, the general meeting of the Polish State Railways…

Radio 357 increased by 50 percent. Deposit how to cancel

Radio 357 has been broadcasting since January 2021, and relies primarily on…

Mai: Municipal councils must determine fees for emptying septic tanks in a rational manner

The municipal council must “rationally” set the upper rates of fees for…

What happens to worn-out wind turbine blades? It must be replaced every 20 years

Researchers say wind turbine blades can be reused as bridges, telephone towers…